Mechanic's Lien Guide
Nebraska Mechanic's Lien Guide
Lien deadlines, notice requirements, and filing procedures for contractors, subcontractors, and suppliers in Nebraska.
Nebraska Lien Deadlines
Preliminary Notice
Not required, but highly recommended before work begins.A "Notice of Right to Assert Lien" can be sent after entering into an agreement and before work begins. The benefit is it preserves a larger "unpaid balance" on the general contract, giving your future lien claim a greater chance of being secured for the full amount you are owed, rather than only the unpaid balance owed to the party you contracted with.
Notice of Intent
Not requiredRecommended to send a Notice of Nonpayment 10-30 days prior to filing the lien.
Mechanic's lien
120 daysMust be filed within 120 days of last work. Enforcement must be initiated within 2 years of lien filing. However, the project owner can shorten this deadline to 30 days by written demand. Mechanic's liens cannot be extended in Nebraska.
Calculate your Nebraska Mechanics Lien Deadline
Your project
DISCLAIMER: These deadlines are pulled from recent lien laws, but you should consult a lien expert or lawyer to understand the deadlines specific to your situation.
Nebraska deadlines
Showing deadlines for a Subcontractor. Deadlines can vary by role.
Enter your project dates on the left to calculate exact deadline dates.
Mechanics Lien Filing
120 days from last furnishing
Enter project dates to calculate
Enforcement (foreclosure)
2 years after filing the lien
Calculated once you record the lien
Nebraska Lien Guide
Preliminary Notice & Notice of Intent
Preliminary Notice: Not required in Nebraska, but highly recommended for subcontractors and suppliers. Notice of Intent to Lien: Not required in Nebraska, but recommended to send "Notice of Nonpayment" 10-30 days before lien.
Who Can File a Mechanic's Lien
Contractors, subcontractors, suppliers, architects, and designers are entitled to mechanic's lien rights in Nebraska.
Who Gets the Notice
No preliminary notice required, but highly recommended. If given, it goes to the project owner.
Information Required
Information needed to file a mechanic's lien in Nebraska includes: - Project owner's name - Claimant's information - Description of the property - Amount owed - Description of the work or materials
Nebraska Public Works
In Nebraska, a mechanic's lien on public works projects is not available. Subcontractors and suppliers can file suit on a payment bond. The bond cannot be less than the contract value except for certain state and local projects below a certain dollar threshold. Parties that do not have a direct contractual relationship with the contractor must give written notice within 4 months of last work. Suit must be filed within 1 year of final settlement of the general contract (if claimant unpaid within 90 days of last performance).
Nebraska Lien Statutes
Official Resources
Protect Your Cash Flow
Filing a mechanic's lien is the last resort. Billd helps you get paid faster so you can focus on building.
Get StartedRelated Articles
For more insights on protecting your payment rights and navigating lien laws, read these articles below.
The Billder's Bulletin
Construction finance intelligence, delivered monthly.
Join thousands of construction executives getting the Billder's Bulletin.